A total station combines an electronic theodolite and EDM to measure horizontal angles, zenith angles and slope distances. A reliable workflow is: check the instrument, set up over known control, orient to a backsight and check a second point, observe on both faces, reduce the observations, then compute and check coordinates before leaving site.

Definition

Total station: an instrument that measures horizontal and vertical angles and slope distances electronically and computes coordinates.

  • Observe face left and face right
  • Check a second known point
  • Record HI and target height
  • Set prism constant and ppm

Before going to site

  • Check collimation, trunnion axis and compensator index; calibrate the EDM on a baseline.
  • Load control coordinates in the correct CRS and units.
  • Set the prism constant and atmospheric ppm (or enter temperature and pressure).

Setup and orientation

  1. Centre and level over the control point; measure instrument height.
  2. Backsight a second control point and set the orientation.
  3. Measure to a third known point as a check; compare coordinates against tolerance.

Observing

For control, observe each direction on face left and face right and average the readings to cancel collimation and trunnion axis errors. For detail pickup, a single face is usually acceptable. Use consistent point codes so CAD linework can be generated automatically.

After observation

Reduce slope distances (see distance reduction), compute and adjust traverses in the Traverse Adjustment tool, and import points into the CAD / GIS Workspace for drafting.

Step by step

  1. Check the instrument. Perform two-face checks and EDM calibration.
  2. Set up. Centre, level and measure HI over control.
  3. Orient. Backsight known control and check a third point.
  4. Observe. Measure angles and distances; two faces for control.
  5. Close. Re-observe the backsight at the end of the setup.
  6. Process. Reduce, adjust and export coordinates.

FAQ

Why measure on two faces?

Averaging face left and face right cancels the main instrumental errors: collimation, trunnion axis tilt and vertical index error.

How often should I check the backsight?

At the start and end of every setup, and after any disturbance to the instrument.

Tools

Articles

References

  1. Uren, J. & Price, W. F. Surveying for Engineers, 5th ed., Palgrave Macmillan, 2010.
  2. Ghilani, C. D. & Wolf, P. R. Elementary Surveying: An Introduction to Geomatics, 15th ed., Pearson, 2018 (traverse computations and adjustments).

Cite this page

GeoCAD Bridge. “Total Station Survey Workflow.” GeoCAD Bridge Knowledge Center, updated 2026-10-05. https://www.geocadbridge.com/knowledge/survey-total-station-workflow/